62
/ BUILDING DIALOGUE / SEPTEMBER 2017
vertical expansion was Adam Gross, superintendent for JE Dunn. “En-
suring we had a good logistics plan was critical to maintaining the
client experience,” said Gross. “All the work was overhead, so safety for
patients below was a big concern.” Crews installed a 20-foot-tall cano-
py to create a 2,000-square-foot area for pedestrian safety and to create
a drive lane and sidewalk for access. We installed a temporary roofing
system to prevent rain and moisture intrusion as the ninth and 10th
floors were constructed. After evaluating schedule options, HCA elect-
ed to close off the entire adjacent lower floor of the patient tower for
an eight-week period to allow for the work to be completed quickly
instead of keeping the floor operational and extending the construc-
tion duration of the vertical expansion. Concurrently, the team began
replacing the entire emergency power system while keeping patient
care operational. Crews demolished a portion of the existing central
utility plant to create a much larger footprint to accommodate three
2,500 kVA generators. Sequencing of utility shutdowns and decom-
missioning of the existing switch gear coincided with installation of
new equipment. During the most critical switchovers, the schedule
was managed on a minute-to-minute basis.
“We rely heavily on a team mentality and we involve our trade
partners on how to overcome the toughest issues,” said Gross. “We are
very fortunate that HCA values early involvement of subcontractor
input.” The team replaced one of the existing chillers during the win-
ter when there was no demand for service. The new 600-ton chiller
was shipped in sections due to space constraints in the chiller room.
The new chiller was then reassembled on site by the mechanical con-
tractor so it could be easily maneuvered into the chiller plant.
JE Dunn was also tasked with the infill of two floors below the Crit-
ical Care Unit of the hospital, which totaled 21,000 sf of core and shell
space. The area was in-filled in what was the old valet parking lot. To
the west of the infill area was the current loading dock, and on the
east is the main exit from the front door of the hospital. In order to
keep access and egress to the hospital in service, the crews construct-
ed a temporary road to route traffic through the north half of the
CCU while also rerouting and tying in the facilities’ city ditch to the
perimeter of the building. All construction activities were strategi-
cally scheduled around Colorado’s water season and our other site
activities to avoid project delays. To maintain the hospital’s high ex-
pectation toward its clients’ experience required strategic planning of
all the logistics.
“We really had nowhere to go, so getting the trades to buy-in into
odd schedules (days and hours) was necessary for timely completion,”
Gross stated. “Our ask to the trade partners is to think about the pa-
tient first and the work second.”
The newest and future construction activities for Swedish are well
underway. Most health care projects will typically involve an addition
or expansion in the effort to expand their bed count. “The work the
team is completing today is rare,” Brisebois said. “It’s a major interior
renovation which touches several floors concurrently and the hospi-
tal is not adding a single bed.” Brisebois feels very fortune to have an
experienced team that understands the drill with health care work
and is extremely customer-oriented. He has a deep understanding of
the complexities project teams must deal with from his days on the
contractors’ side of the table working with HCA as his client. In re-
sponse, Brisebois said, “The first day is always very simple because you
go in with a plan, but inevitably the plan will change.”
As the Perkins+Will teammembers discuss the future master plan-
ning for the Swedish campus, they keep an adaptable and flexible
attitude. Frazier leverages the team’s on-site knowledge to gain an un-
derstanding of what happens day-to-day, hour-by-hour as she leads
the next major planning efforts for HCA.
“You can’t know the existing issues until you’re in it,” Frazier said.
“You just stare into another solution on the fly and be as resilient and
adaptable with problem solving.”
\\
/ Swedish Medical Center: /
PHOTOS:
Frank Ooms
OPENING ART TOP:
Swedish Medical Center’s completed vertical
expansion of the ninth and 10th floors
OPENING ART BOTTOM:
.
Nurse’s station on the new 10th floor addition
of hospital tower.
ABOVE:
Critical Care Unit lobby on the newly
renovated fourth floor in the main building